Client

Shaftesbury Chinatown Ltd

Location

Theatreland - Central London

Contractor

Roots Contractors Ltd

Contract sum

£1.52 million

Onsite duration

54 weeks

Description

Conversion of small offices either side of a central staircase core, to create six spectacular new apartments.

Client brief

To transform small offices into apartments.

Our role

Prepare proposals to allow for a change of use of the upper floors. Carry out the role of contract administrator through the specialist the reconfiguration of the must rebuild interior of the prominent building whilst retaining much of the original historic exterior. Including relocation of the lift core. Within our remit was to formulate the tender documentation, together with both financial control and contract administration of the building project.