Client

Shaftesbury Covent Garden Ltd

Location

38 St Martins Lane, London WC2

Contractor

Roots Contractors Ltd

Contract sum

£2.3 million

Onsite duration

54 weeks

Description

Refurbishment of the existing offices on the first and second floor. Whilst the third floor existing offices were converted into four high-end flats including one duplex penthouse on the fourth floor.

 

Client brief

Refurbish common parts and offices including change of use of top two floors to residential.

Our role

Full design package to obtain local authority consents, preparation of the tender package and onsite contract administration/project management from concept through to completion.